The installation of the static load module should pay attention to the following three points:

1. The static load weighing module is installed with a fixed module, a semi-floating module and one or two floating modules.

2. The semi-floating module should be installed on the opposite corner of the fixed module. The distance between the two mounting points is the longest between all mounting points.

3. The support feet of the container should be reinforced to prevent outward stretching due to deformation of the container.

Weighing module www.czhoto.com

Relevant articles
Related products
  • HT-0720
    HT-0720
  • HT-FWC Stainless steel static load weighing module
    HT-FWC Stainless steel static load weighing module
  • HT-SB Cantilever beam load cell
    HT-SB Cantilever beam load cell
  • FWQ Economic weighing module
    FWQ Economic weighing module
  • HT-GW Column weighing module
    HT-GW Column weighing module
  • HT-3123PTN Weighing control instrument
    HT-3123PTN Weighing control instrument
  • HT-600 Weighing control instrument
    HT-600 Weighing control instrument
  • HT-0745A Stainless steel load cell
    HT-0745A Stainless steel load cell
Contact Us
Add: No. 91, Hanjiang West Road, Xinbei District, Changzhou City
Mob: 0086-519-89619969/0086-519-85505769
Code: 213125
Fax: 0086-519-85505706
E_mail: hoto@dzhq.cn
QR code
Mobile website
WeChat
Submission
Copyright © 2018 Changzhou Hoto Electronic Weighing Apparatus Co., Ltd. All rights reserved Support:Eastnet [Manage]
Top
Baidu
ac米兰app官方下载